Hi Experts,
I am running a scenario with QM in EWM and when I take usage decision with partial acceptance and partial rejection in /SCWM/QINSP following things happen. We posted GR for 5 nos. and took usage decision of 3 nos. acceptance and 2 nos. rejection in EWM.
1.System is forcing to enter exception code
2.Warehouse task created in wrong quantities
3.UOM for acceptance quantity is alternate UOM.
4.The update of usage decision is sent to ECC and it goes in error in queue with error e.g."PU Ordered quantity exceeded by 3,175 GL : 1016551".
Please let us know if you have worked with this scenario and it worked for you. If there is SAP note please let me know.
Thanks for your support
Regards,