Hi Experts,
Pls throw some light and give me inputs in solving my issue.
My Scenario is STO (Plant to Plant within comp.code) integrated with EWM:
1. Created STO: (Supplying plant/sloc and Receiving plant/sloc are EWM managed)
2. Created Outbound delivery: Distributed successfully to EWM
3. Done the all activities in EWM like Picking, Loading & Goods issue
4. In ECC stock is not reduced and no update of Mat.doc/indbound, and still the ECC Outbound delivery is in open status
5.If I want to try post MIGO wrt Outbound or STO PO is also not possible as my Outbound delivery is greyed out (once its distributed, its not allowing to change).
Thats how I got struck. Dont know what to do, If I am right I followed the correct process.
Thanks to All
Srinivas