Dear Experts,

 

We will be implementing Pick Pack Pass due to conveyor setting in the warehouse. And after all sub-WOs are completed, we would like the pick-HU pass through a staging point(bin 0020-04-04-B in below picture). But after the pick-HU enters the bin, the subsequent WT to GI-zone is not created automatically. I have try a few external steps for this purpose but none of them works. Please kindly share some thoughts.

 