Hi
I have combined Process Oreinted storage control and Layout Oriented Storage control.
Unloading
Packing
Putaway
These are threee steps in Inbound Storage Process.
Since the Packed product is to routed through ID Point , Layout oriented Storage Control is also activated.
so the steps should be
Unloading
Packing
I-Point --> standard id point storaeg type 0081 ( intermediate for final location 0080 )
Putaway
But the proccess ends at I-Point.
The Hu after packing is being moved to I-Point correctly. But the Process ends there and next warehouse task i.e. final putaway warehouse task is not being created automatically when we confirm WT from Packing to I-Point.
Any Idea what is missing ?
Thanks in advance.
Regards / Vinod