Hi guys,
Now I met a tricky problem for EWM-QM integration. According to current understanding, the key point is whether installation name has to be identical with logical system name?
We define business system in the path: SPRO->SCM Extended Warehouse Management->Extended Warehouse Management->Interfaces->ERP Integration->General Settings->Define Business System, here we maintain business system ERP_001 assigned to logical system EPDCLNT001
Then define installations in the path: SPRO->Cross Application Components->Quality Inspection Engine->Central Settings->Communication with an External QM System->Define External QM Systems
Then Assign the installation to warehouse, we tried to define the installation as ERP_001 or EPDCLNT001, but neither works, we always got an error when we do GR for inbound delivery: Unable to determine RFC destination for QM connection; check Customizing
I understand that the installation must be identical to the business system (SAP Note 1278425). However, although the business system has a logical system assigned which is identical to the installation, the system compares the installation with business system instead of the logical system. It seems this logic only applies to the integration with QM, for other ERP integration, we can set business system freely.
Regards
Danny